Land dispute stalls Sonahat Bridge approach road for 7 years, public sufferings mount   ​

Land dispute stalls Sonahat Bridge approach road for 7 years, public sufferings mount  ​

Bhurungamari (Kurigram) Correspondent

Construction of the eastern approach road for the new Sonahat Bridge over the Dudhkumar River in Bhurungamari upazila has remained stalled for seven years due to a land ownership dispute between Bangladesh Railway and local residents, causing severe hardship for commuters and land port traders.

To keep operations running at the Sonahat Land Port, the Roads and Highways Department (RHD) began constructing the 645.015-meter RCC girder bridge in 2019 at an initial cost of Tk 136.33 crore, south of the British-era rail bridge built in 1887 that expired four decades ago. Although slated for completion in 2021, the project remains unfinished despite four deadline extensions and a Tk 7 crore budget hike.

Commuters are forced to use the dilapidated old bridge at high risk. Early Tuesday (November 17), a steel plate on the old bridge's eastern end collapsed under a stone-laden truck, halting heavy vehicular movement.

Sources said the bottleneck centers on roughly 6 acres (571.23 decimals) of land across six plots in Gonairkuti mouza of Banga Sonahat union. While 38 local shareholders claim the land as ancestral property backed by three land records, the Lalmonirhat Divisional Office of Bangladesh Railway has claimed ownership in a letter to the Kurigram Deputy Commissioner. Three inter-ministerial meetings have failed to break the deadlock.

Local claimants, including Abdul Jalil and Abed Ali, warned they would become homeless if evicted without fair compensation.

Project Manager Shamim Ahmed of contractor MM Builders and Engineers Ltd. said the main bridge and western approach road are nearly finished, and the eastern section would take six months to complete once the land is handed over.

RHD Sub-Divisional Engineer Mehedi Hasan Sarker noted that 80 percent of overall bridge work is complete. Kurigram Deputy Commissioner Annapurna Debnath confirmed that authorities are working to resolve the acquisition impasse swiftly to ease public suffering. Lalmonirhat Railway Estate Officer Manzur Alam could not be reached for comment.

Comment / Reply From

Vote / Poll

ফিলিস্তিনের গাজায় ইসরায়েলি বাহিনীর নির্বিচার হামলা বন্ধ করতে জাতিসংঘসহ আন্তর্জাতিক সম্প্রদায়ের উদ্যোগ যথেষ্ট বলে মনে করেন কি?

View Results
হ্যাঁ
0%
না
0%
মন্তব্য নেই
0%

Archive

Please select a date!